Quick Answer: As of November 2026, the roughly $1.4 billion EverBank Stadium “Stadium of the Future” renovation is on schedule for an August 2028 opening. The City of Jacksonville is committing $775 million and the Jaguars $625 million plus overruns not caused by the city. The team is playing 2026 at about 42,465 seats and moves to Orlando for 2027, while the Shipyards district fills in next door.
Jacksonville’s biggest public-private construction job is well past the planning stage. A steel truss weighing about a million pounds now spans the north end zone, upper-bowl seats are gone for the season, and a marina, office building and luxury hotel are rising next door. Here is where things stand as of November 19, 2026.
What Is the Stadium of the Future Deal?
The Jaguars unveiled the “Stadium of the Future” concept in June 2023, with HOK as designer. Jacksonville City Council approved the stadium agreement on June 25, 2024, by a 14-1 vote with two abstentions, through Ordinance 2024-0904. The legislation totals about $1.45 billion including $56 million for riverfront parks and a flex field. NFL owners gave unanimous final approval on October 15, 2024.
The project rebuilds the existing 1995 stadium rather than replacing it, adding a transparent canopy, concourses four times wider, new seating at every level and new building systems. The Jaguars say the canopy should cut radiant heat in the bowl and concourses by 10 to 15 degrees Fahrenheit versus direct sunlight.
How Is the $1.4 Billion Cost Split?
The city and the team each put $625 million toward the joint renovation. The city adds $150 million for deferred maintenance and capital improvements, bringing the public stadium commitment to $775 million. The Jaguars cover overruns not caused by city delays.
| Funding component | Amount | Responsible party |
|---|---|---|
| Joint stadium renovation share | $625 million | City of Jacksonville |
| Joint stadium renovation share | $625 million | Jacksonville Jaguars |
| Deferred maintenance and capital improvements | $150 million | City of Jacksonville |
| Total public stadium commitment | $775 million | City of Jacksonville |
| Riverfront parks and flex field | $56 million | City of Jacksonville |
| Overruns not caused by city delays | Open-ended | Jacksonville Jaguars |
How Is the City Paying Its Share?
No new tax was levied for the stadium. According to the Jacksonville Daily Record, the city moved about $600 million of projects out of its borrowing-based Capital Improvement Plan and onto Better Jacksonville Plan sales tax revenue, freeing up capital plan capacity for the stadium. The Better Jacksonville Plan was set to sunset early in 2026 so that a pension-liability sales tax could start sooner. The Council Auditor estimated a net $25 million in annual general fund savings from the shift: about $40 million in debt payments avoided, minus $15 million in pension contributions.
What Does the Lease Require?
The lease runs 30 years with $1 million in annual base rent from the team. The non-relocation terms are strict. If the Jaguars leave in years 1 through 14, they repay 100% of the city’s investment. That figure then drops 6.25 percentage points a year, from 93.75% in year 15 to 6.25% in year 29.
Is the Project Over Budget?
In December 2025, city Chief Administrative Officer Mike Weinstein told City Council the project was tracking about $100 million in overruns. Team President Mark Lamping said that month the team is “generally responsible for cost overruns” and that the number was still moving. In a February 25, 2026 update, Lamping said the project will exceed $1.4 billion and that the final figure will not be clear until more interior work is done.
Building permits give a partial view of the hard costs. On February 27, 2026, the city issued the fourth and largest “issued for construction” permit, worth $696.5 million and covering eight levels and 652,735 square feet. Combined with about $640 million in permits issued since the foundation approval on December 10, 2024, permitted construction value now tops $1.33 billion. Permit values exclude soft costs and some owner-direct work.
What Is the Construction Status as of November 2026?
Work began in February 2025, and the team has said consistently that the project is on schedule. Lamping put it at about 10% complete in mid-December 2025 and about 15% complete in late February 2026. The Jaguars’ project FAQ now says more than 140 local contractors and subcontractors are working on the site, with an average of more than 700 local employees on site daily. By August 2026, more than 1.5 million work hours had been logged.
Which Milestones Have Been Reached?
| Date | Milestone |
|---|---|
| June 25, 2024 | City Council approves stadium agreement, 14-1 |
| Sept. 10, 2024 | Council approves $94 million city community benefits funding, 13-2 |
| Oct. 15, 2024 | NFL owners unanimously approve the renovation |
| Feb. 2025 | Construction begins |
| Feb. 27, 2026 | Final and largest permit, $696.5 million, issued |
| Mar. 31, 2026 | NFL owners approve one-year Orlando lease for 2027 |
| Aug. 2026 | Wider concourse sections, new gates and stairwells shown to fans; 1.5 million work hours logged |
| Late Oct. 2026 | North end zone truss (about 1 million pounds) lifted into place over 72 hours |
| Early 2027 (target) | Roof steel complete; shade structure work to follow in 2027 |
| Aug. 2028 (target) | Grand opening |
Action News Jax reported October 29 that most expanded concourse areas had been built and poured but were not yet open, South End Zone Club concrete was poured, and the southwest core electrical system was finished.
Who Is Building It?
The Jaguars selected a joint venture of AECOM Hunt and Barton Malow as construction manager, announced May 16, 2025; HOK is the architect. Early work included demolishing a Gate 1 skybridge, two escalator towers and three light towers, plus relocating underground utilities and laying roof and concourse foundations.
How Does Construction Change the Jaguars’ Schedule?
The team says a stop-and-start four-year renovation would have added upwards of $190 million, so it chose two years of heavy disruption. For 2026, the Jaguars took 27,308 seats offline, including 22,005 upper-bowl seats, which leaves capacity at 42,465. The 2026 slate includes two preseason and six regular-season home games in Jacksonville, plus two home games in London in consecutive weeks.
On March 31, 2026, NFL owners unanimously approved a one-year lease for the Jaguars to play the 2027 season at Camping World Stadium in Orlando, about 140 miles away. At least one 2027 game is planned for London. Other events are moving too: the Florida-Georgia game goes to Atlanta in 2026 and Tampa in 2027, and its Jacksonville return is extended through 2031. The TaxSlayer Gator Bowl moves to Gainesville for its 2027 edition, and Daily’s Place amphitheater is closed for two years.
What Will the Finished Stadium Hold?
More than 63,000 seats, expandable to more than 70,000, per the team and construction manager, versus 67,814 originally. Figures cited at the 2024 vote were 62,000 expandable to 71,500.
What Do the Community Benefits Actually Commit?
The Jaguars and the city describe a $300 million community benefits agreement, split $150 million each, as the largest in NFL history. The city’s side is the $56 million for parks and the flex field plus $94 million approved September 10, 2024: $40 million for the Eastside over seven years, $40 million countywide over 15 years and $14 million divided equally among the 14 Council districts. It targets affordable housing, workforce development and homelessness services. The Jaguars’ $150 million is spread over 30 years, with disbursements planned to begin in 2028.
Implementation has been slower than the headlines. A Council special committee, chaired by Raul Arias with Eastside Council Member Jimmy Peluso as vice chair, began meeting in May 2025 on how to structure the city’s spending. Both favored an Eastside tax increment financing district for long-term funding. An early countywide allocation was $3 million in April 2025 for a University of North Florida esports arena, counted as workforce development.
How Many Jobs Does the Project Support?
The Jaguars cite an economic impact study projecting a one-time impact of $2.4 billion from construction. The study says that spending supports 17,760 full- and part-time jobs and generates about $70.7 million in state and local taxes, along with a 30-year impact of $26 billion through 2057. These are modeled estimates from a team-commissioned study, not headcounts.
What Is Happening in the Downtown District Around the Stadium?
Jaguars owner Shad Khan’s Iguana Investments and the city’s Downtown Investment Authority (DIA) are building in parallel along the riverfront west of the stadium. The Shipyards project, first approved in 2021, pairs a Four Seasons hotel and residences with a six-story office building that now serves as Jaguars headquarters, a public marina and park space.
| Project | Key figures | Status (Nov. 2026) |
|---|---|---|
| Four Seasons Hotel and Private Residences | About 170 rooms, 26 residences from $4.7 million; $360 million Goldman Sachs construction loan | Under construction; opening tentatively 2027; city completion deadline June 30, 2027 |
| Shipyards office building | Six stories, next to hotel | Open; Jaguars business operations moved in early 2026 |
| Met Park Marina | 78 slips with power and water | Docks opened Aug. 12, 2026 |
| Shipyards West Park | 10 acres; $74.7 million needed, $54.7 million in proposed FY2025-26 budget | Design and permitting |
| Metropolitan Park redesign | 18-plus acres; $12 million available for fall 2026 construction | Construction slated to begin fall 2026; finish likely 2028 |
| Museum of Science and History (MOSH) | 125,000 sq ft; $50 million city commitment; $150 million construction fundraising goal | Groundbreaking expected early 2027 |
What Public Incentives Support the Shipyards?
A DIA breakdown reported by Jax Today in November 2025 put the city’s total Shipyards incentive package at $133,896,354, up from $114.4 million originally. Ordinance 2025-0815 raised the maximum Recapture Enhanced Value grant for the Four Seasons to $56,581,200 over 20 years. It also lifted the hotel’s minimum capital investment to $373.962 million and moved the hotel completion deadline from June 30, 2026 to June 30, 2027. Other items include a $25.8 million hotel completion grant, $12.4 million in land and $9.8 million for fire station and dock relocation. DIA projected $152.8 million in city tax and economic benefits, a net benefit of about $18.9 million, or $1.14 returned per dollar invested.
Is the Four Seasons Behind Schedule?
Yes, relative to the original plan. Action News Jax reported in March 2026 that the hotel’s original completion target of the end of 2025 had been extended twice, with completion then set for June 2027. In February 2026, Bloomberg reported that the Khan family had secured a $360 million construction loan from Goldman Sachs’ private bank, the largest loan on record in Jacksonville. In September 2026 the hotel named senior leadership ahead of a tentative mid-2027 opening.
How Do the Riverfront Parks Tie Back to the Stadium Deal?
City staff have said the stadium agreement’s community benefits fully fund final construction of Shipyards West Park, Metropolitan Park and Riverfront Plaza. Met Park’s redesign adds a tailgate plaza, a concert-scale performance lawn and a “resilient river edge” with boardwalks. MOSH, relocating to a 2.5-acre Shipyards site, had raised almost $100 million toward its construction goal by September 2026.
What Should Northeast Florida Businesses Watch Next?
Watch four markers: roof steel completion in early 2027, the final overrun figure, the Four Seasons’ June 30, 2027 completion deadline and the August 2028 reopening. For hospitality, food service and event businesses near downtown, the 2027 season in Orlando means a full year without NFL game days in Jacksonville, then a larger year-round venue beside a hotel, marina and parks. For contractors and suppliers, interior fit-out over the next 18 months is where much of the remaining permitted work sits.
Frequently Asked Questions
How much is Jacksonville paying for the Jaguars stadium renovation?
The city committed $775 million: $625 million toward the joint renovation and $150 million for deferred maintenance and capital improvements. Separately, it committed $56 million for riverfront parks and a flex field and $94 million in other community benefits.
When will the renovated EverBank Stadium open?
The target grand opening is August 2028, in time for the 2028 NFL season.
Where will the Jaguars play in 2027?
At Camping World Stadium in Orlando, under a one-year lease approved unanimously by NFL owners on March 31, 2026.
Who pays if the stadium goes over budget?
The Jaguars are responsible for cost overruns not caused by city delays. City officials cited about $100 million in potential overruns in December 2025, and the team has said the cost will exceed $1.4 billion.
Sources and Further Reading
- It’s a deal: Jacksonville City Council approves stadium agreement with Jaguars — Jacksonville Daily Record
- ‘Legacy’: Jacksonville commits $775 million to Jaguars stadium renovation — Florida Politics
- History in the making: Council approves community benefits deal with Jaguars — Jacksonville Daily Record
- Despite potential cost overruns, ‘Stadium of the Future’ on schedule — Jacksonville Daily Record
- City issues ‘final and largest’ Stadium of the Future permit, topping $696 million — Jacksonville Daily Record
- NFL owners approve Jacksonville Jaguars’ 2027 move to Orlando — Jacksonville Daily Record
- ‘On schedule, but we have a long, long way to go’: Jaguars provide update on stadium construction — Action News Jax
- Jaguars return home with concourse crowding fixes, million-pound steel truss in place — Action News Jax
- Jaguars unveil first look at renovated EverBank Stadium — News4JAX
- Jaguars prep for home season under construction — NFL.com
- Stadium of the Future FAQs — Jacksonville Jaguars
- AECOM Hunt–Barton Malow joint venture selected as construction manager for Stadium of the Future — AECOM
- Special committee ponders plan for long-term support of Eastside improvements — News4JAX
- Jacksonville’s riverfront transformation: six new parks to reshape Downtown — Downtown Investment Authority
- Four Seasons tax rebate increase and Shipyards incentive breakdown — Jax Today
- Jags office tower done, Four Seasons construction experiencing delays — Action News Jax
- Four Seasons hires GM, commercial director ahead of 2027 planned opening — Action News Jax
- Khans secure record loan for Jacksonville Four Seasons — Bloomberg
- Met Park Marina opens docks next to EverBank Stadium — News4JAX
- Jacksonville unveils latest concepts for Met Park revamp — AOL
- MOSH construction deadline extension and Northbank museum renderings — Jax Today